This project was an additional headmaster's
building with a library, music center, life science training center, art and
several other specialized classrooms. This 3 story building was utilized to
expand the existing school to accommodate the growing student enrollment.
This project provided a unique requirement for unique lighting requirements
and attention to detial. This project contained several millwork arrangements
which required extraordinary coordination to provide the desired result. The
project had 1-600A utility style switchboard, 600+ lighting fixtures, 8
panelboards, 150+ point fire alarm system, public address system, security
system, and 500+ branch circuits.
|